CFD simulation for the new data centre “Lupin3”

Project overview

The company Green Datacenter AG is constructing a 6-storey new build in the industrial quarter of Lupfig (canton of Aargau), which – in addition to offices – will be used specifically for a data centre and associated utility rooms. With the aid of various construction scenarios, a CFD simulation (Computational Fluid Dynamics) was used to show that the challenging temperature requirements in the data centre can be met by means of the selected mechanical ventilation system.

Client

Green Datacenter AG

Our services

Integrated building services engineering planning with BIM. Performance of a CFD simulation for one of the machinery rooms for optimised design of the mechanical ventilation system.

Similar projects