As the world’s longest rail tunnel, the Gotthard Base Tunnel represents a planning challenge in many different disciplines. The core of the project comprises two 57-kilometre-long single-track tunnel tubes and the open sections of 3 kilometres in the north and 7 kilometres in the south. The track project encompasses ballasted track, slab track and points with drives, light signals and heating systems.

Expertise involved

Track design

Client

AlpTransit Gotthard AG

Our services

Project planning and support for client in all matters relating to track, preparation of service contracts, implementation as well as inspection and commissioning of an extensive and complex railway system.